Date | Status | Code | Description | Ref | Location | Comments |
1/4/2024 | Transfer | FoamSysFin6 | Correction(s) #3 | <div>Correct the following item(s):</div><div><br></div> | | Complete flushing in the spring. |
1/4/2024 | Transfer | FoamSysFin2 | CCO Approved | CCO Approved for Foam System | | Foam system approved for CCO till June 30, 2024. Ok to use the tank |
1/4/2024 | Transfer | FoamSysFin4 | Correction(s) #1 | <div>Correct the following item(s):</div><div><br></div> | | Complete signage |
1/4/2024 | Transfer | FoamSysFin5 | Correction(s) #2 | <div>Correct the following item(s):</div><div><br></div> | | Complete hydrostatic test in the spring. |
1/4/2024 | Transfer | FoamSysFin8 | Install Cert | <div>Provide Installation Certification and test report.</div><div><br></div> | | Provide final install cert. |