Date | Status | Code | Description | Ref | Location | Comments |
8/28/2023 | Corrected | Correct Below | * | | Suite 3, 4 | Proper labeling for Panel B Short Circuit Current Rating. 2020 NEC 408.6 |
8/28/2023 | Corrected | Correct Below | * | | Suite 3, 4 | Support MC and cable off of T-Bar ceiling. |
8/28/2023 | Corrected | Correct Below | * | | Suite 4 | Breaker Blanks needed for panel B |
8/28/2023 | Corrected | Correct Below | * | | Suite 5 electrical room | Ko seal needed for 18" X 18" J-Box |
8/28/2023 | Corrected | Correct Below | * | | Suite 5 | Emergency lighting not functioning. |
8/28/2023 | Transfer | Correct Below | * | | Suite 5 | Water Heater disconnect and connection to water heater remains to be installed. OCP for water heater appears to be oversized. |
8/28/2023 | Transfer | Correct Below | * | | Suite 5 bathroom | shower light remains to be installed. Light needs to support to structure. Flat metal plates that can be screwed to the grid are designed for this install. |
8/28/2023 | Transfer | Correct Below | * | | Suite 5 | Prints show an egress light outside of front door remains to be installed. Exit sign is shown to have dual lights for egress lighting on the print. |
8/28/2023 | Transfer | Correct Below | * | | Suite 5 | Prints show switch and light to be installed in electrical room. Light installed in electrical room shall not have ceiling tile support fixture. Light needs to support to structure. Flat metal plates that can be screwed to the grid are designed for this install. |