Inspection #: 738581
Inspection Type: Sprinkler Hydrostatic Test
Inspector: D.Meneses
Result: Approved
Comment: Hydro test for basement, 1st floor, and 1st floor Mezz. Contact Patrick @ 907-529-7702 to schedule Requested by: Patrick Noblett 907-529-7702 patrick@accelfire.com

Inspection Corrections
DateStatusCodeDescriptionRefLocationComments
1/12/2023 FireSprkHydro2Partial Hydrostatic TestPartial approval for fire sprinkler system hydrostatic test for the following area(s):basement, 1st floor, and 1st floor BAll okay. 
10/6/2022 FireSprkHydro2Partial Hydrostatic TestPartial approval for fire sprinkler system hydrostatic test for the following area(s):Penthouse and 9th FloorAll okay to proceed.  Tested to 260 PSI.
8/2/2022 FireSprkHydro2Partial Hydrostatic TestPartial approval for fire sprinkler system hydrostatic test for the following area(s):South standpipe and floors 2-8 hydrookay to proceed, I could see no issues at the time of this inspection.
5/10/2022 FireSprkHydro2Partial Hydrostatic TestPartial approval for fire sprinkler system hydrostatic test for the following area(s): Okay to proceed. Hydro tested from mainline inlet to 1st valve at sprinkler tree.