| Date | Status | Code | Description | Ref | Location | Comments |
| 8/17/2022 | | FireSprkBracing1 | Approved - Fire Sprinkler Bracing | Approved fire sprinkler system bracing | | All corrections made from last report, okay to proceed. |
| 7/13/2022 | | FireSprkBracing4 | Correction(s) #3 | <div>Correct the following item(s):</div><div><br></div> | | Re-inspection required after special inspection is completed and observation of attachments can be made. |
| 7/13/2022 | | FireSprkBracing2 | Correction(s) #1 | <div>Correct the following item(s):</div><div><br></div> | | Sheet rock installed before inspections. Remove all sheetrock so proper inspection can be done of hangers and bracing for post installed concrete anchors. |
| 7/13/2022 | | FireSprkBracing3 | Correction(s) #2 | <div>Correct the following item(s):</div><div><br></div> | | Required Special Inspection not completed for post installed concrete anchors per the requirements of 2018 IBC Section 1704, 1705.3 and Table 1705.3 #4. Pay Fine of $425.00 before final, for failure to perform required special inspection per AMC 23.10 Table 3-O #2. |