Date | Status | Code | Description | Ref | Location | Comments |
4/1/2022 | Transfer | Correct Below | * | | Common area, corridor | Inspection for corridor area. Common area work on plans was noted as incomplete on previous inspection. No record of electrical rough inspection for this area. New lighting types G and F2 at common area (corridor) ceiling covered without inspection. Provide access to effectively inspect wiring to new lights above ceiling. Depending on location of boxes or other wiring methods above ceiling, access panels or additional inspection access locations may be required. Multiple electrical contractors noted on permit. |
3/11/2022 | Transfer | Correct Below | * | | Various equipment throughout. | Disconnects required per 422.30 and 31. |
3/11/2022 | Transfer | Correct Below | * | | Unit heater. | Incomplete. If not to be installed, provide Field change order to remove from plans. |
3/11/2022 | Corrected | Correct Below | * | | Various equipment. | Cord connection with attachment plug required. Cord not suitable for fixed wiring method. |
3/11/2022 | Transfer | Correct Below | * | | Rear ceiling | Heat trace incomplete. |
3/11/2022 | Transfer | Correct Below | * | | Common area work on plans incomplete. | |
3/11/2022 | Transfer | Correct Below | * | | Water heater installation manual | Required overcurrent device-65 amp. |