Inspection #: 676311
Inspection Type: Final Fire Inspection
Inspector: M.Warren
Result: CondAppr
Comment: I have a 10am disruption notice scheme with AIA. Please meet at the tunnel at 10am Monday morning. Thank you, Grady Requested by: Grady Putman 227-6446 Gputman@rhcak.com

Inspection Corrections
DateStatusCodeDescriptionRefLocationComments
8/16/2021 Fire 2CCO approvalFire Final approved for CCO Items addressed and corrected from above. Tunnel use CCO approved until 12/30/22. Provide a temporary exit sign on the east end outside of the tunnel with arrow to exit saying "emergency exit only".
8/10/2021CorrectedFire 19Correction(s) #6Please correct the following: This inspection may not include all issues required to obtain a CCO.
8/10/2021CorrectedFire 18Correction(s) #5Please correct the following: verify functionality of newly installed/relocated fire alarm devices in and adjacent to tunnel. Test in presence of inspector or provide affidavit of install & testing of devices.
8/10/2021CorrectedFire 15Correction(s) #2Please correct the following: Complete construction to a level that is safe for public to include cover open wiring @ elevator lobby, remove tape over smoke detectors for elevator @ all levels. repair inop emergency light in tunnel, complete all tunnel framing, walls, & interior finish ratings.
8/10/2021CorrectedFire 17Correction(s) #4Please correct the following: Tunnel construction does not appear to be compatible with building construction.  Use of wood studs & walls if allowed are typically required to be covered with sheet rock and/or sprinklered.
8/10/2021CorrectedFire 16Correction(s) #3Please correct the following: Plastic sheathing used as dust barrier is required to meet IFC chapter 8 for interior finish for smoke development & flame spread.  Submit documentation prior to install.  Remove materials that are not approved or do not meet requirements.
8/10/2021CorrectedFire 13Correction(s) #1Please correct the following: Clarify scope of work.  Provide tunnel safety plan & details to include any approved change orders.