| Date | Status | Code | Description | Ref | Location | Comments |
| 8/10/2021 | Transfer | Fire 19 | Correction(s) #6 | Please correct the following: | | This inspection may not include all issues required to obtain a CCO. |
| 8/10/2021 | Transfer | Fire 18 | Correction(s) #5 | Please correct the following: | | verify functionality of newly installed/relocated fire alarm devices in and adjacent to tunnel. Test in presence of inspector or provide affidavit of install & testing of devices. |
| 8/10/2021 | Transfer | Fire 17 | Correction(s) #4 | Please correct the following: | | Tunnel construction does not appear to be compatible with building construction. Use of wood studs & walls if allowed are typically required to be covered with sheet rock and/or sprinklered. |
| 8/10/2021 | Transfer | Fire 15 | Correction(s) #2 | Please correct the following: | | Complete construction to a level that is safe for public to include cover open wiring @ elevator lobby, remove tape over smoke detectors for elevator @ all levels. repair inop emergency light in tunnel, complete all tunnel framing, walls, & interior finish ratings. |
| 8/10/2021 | Transfer | Fire 16 | Correction(s) #3 | Please correct the following: | | Plastic sheathing used as dust barrier is required to meet IFC chapter 8 for interior finish for smoke development & flame spread. Submit documentation prior to install. Remove materials that are not approved or do not meet requirements. |
| 8/10/2021 | Transfer | Fire 13 | Correction(s) #1 | Please correct the following: | | Clarify scope of work. Provide tunnel safety plan & details to include any approved change orders. |