Inspection #: 671858
Inspection Type: Framing / Ext.
Inspector: H.Kahlstrom
Result: Approved
Comment: Shear wall nailing and straps at West elevation is complete and approved. Contractor is approved to extend the building wrap around the corners as the nailing meets or exceeds the shear nailing schedule.

Inspection Corrections
DateStatusCodeDescriptionRefLocationComments
       