Result: Approved
Comment: Floor Diaphragm nailing grids 9 - 14 level 2 all required diaphragm blocking is in place per plan. Sill plate anchor bolts level 1 area A. ATS rods with their accompanying boundary members are complete. 1 side of shear nailing is complete at level 1 walls. I observed shaft areas at all level 1 units. NOTE: All shaft assemblies will be inspected as work progresses to review interior shear nailing and the different layers of the assembly. SEE SPECIAL INSPECTION REPORTS WITH HIGHLIGHTED AREAS FOR AREAS INSPECTED.