Inspection #: 618580
Inspection Type: Final Electrical
Inspector: M.Green
Result: Correction
Comment: Final inspection for the N10 Gate Improvements. Please call Jay @ 301-2247. 15 minutes prior to inspections. Requested by: Greg Stewart 382-5090 consolidatedconeng@gmail.com

Inspection Corrections
DateStatusCodeDescriptionRefLocationComments
7/8/2020TransferCorrect Below* Panel schedules.Label spare breakers. Verify labelling of panel source of supply.
7/8/2020TransferCorrect Below* Drawing.Shows 40A breaker supplying MOVs. 50A breaker installed.
7/8/2020TransferCorrect Below* Underground j-box metal lid by transformer and panel H-frame.Bonding strap not properly connected to grounding system in box. Use Copper C.
7/8/2020TransferCorrect Below* H-frame pilings driven 20+ feet into the ground.These qualify as grounding electrodes and are required to be connected to transformer XO by a #4 GEC.
7/8/2020TransferCorrect Below* GRC isolated sections emerging from grade below H-frame for XFMR and panel.GRC isolated from metal panels, transformer by liquidtite requires external bonding jumpers around the liquidtight.
7/8/2020TransferCorrect Below* Transformer.No connection from GEC to XO.