Inspection #: 606678
Inspection Type: Electrical Rough
Inspector: E.Widman
Result: Partial
Comment: Pre-inspection performed at ATS 1,2,3 and 12.

Inspection Corrections
DateStatusCodeDescriptionRefLocationComments
4/1/2020Transfer01See inspection comments Pre job inspection for planned location of new panel. Ensure proper working clearances and dedicated equipment space is maintained per 110.26 
4/1/2020Transfer01See inspection comments What is planned interconnection of secondary alternate source to switch gear? Document on plans.  
4/1/2020Transfer01See inspection comments Provide MOA stamped reviewed plans for inspection. Provide one line drawing related to planned work.  