| Date | Status | Code | Description | Ref | Location | Comments |
| 11/27/2019 | Transfer | FNLSG | Final Structural Other | Please correct the following: | new floor penetration for power source | provide documentation of fire pillow assembly for rated floor/ceiling. |
| 11/27/2019 | Transfer | FNLSG | Final Structural Other | Please correct the following: | Roof | Deferred submittal for seismic connection on vent at roof curb. Provide stamped submittal document . Recall for final structural once documents obtained. |
| 11/27/2019 | Transfer | FNLSG | Final Structural Other | Please correct the following: | CT -2 scan | provide special inspection report for any and all post installed anchors per 2012 IBC Chapter 17. DICA & Approved plan shows these requirements on S-1.0 |