| Date | Status | Code | Description | Ref | Location | Comments |
| 10/14/2019 | Transfer | firealarm11 | Fire Alarm approved CCO | Fire Alarm approved for CCO | | Fire alarm approved for CCO till Nov 15 2019 |
| 10/14/2019 | Transfer | firealarm13 | Please correct the following | Please correct the following: | | (1) 11th floor has horn strobe installed and needs strobe only installed in the ceiling (2) Submit change order to show relocated devices, deletions and strobe candla changes on the 11th and 12th floors. (3) Submit as built plans to plan set in fire command center and building main file |