Date | Status | Code | Description | Ref | Location | Comments |
6/27/2019 | Transfer | 01 | See inspection comments | | at panel | circuits involved in this remodel must have dedicated neutrals or have a handle-ties installed |
6/27/2019 | Transfer | 01 | See inspection comments | | at track lights | seismic support wires required for track lights |
6/27/2019 | Transfer | 01 | See inspection comments | | above check out counter | open boxes need covers, MC cable to power pole not supported within 12" of box, existing 1/2" flex between J-boxes not properly supported and box needs a cover |
6/27/2019 | Transfer | 01 | See inspection comments | | at check out counter | need to verify that ground to IG receptacles is isolated |