| Date | Status | Code | Description | Ref | Location | Comments |
| 11/2/2017 | Transfer | Correct service item below | * | | MCC building service | bond service entrance conduits with #3/0 cu |
| 11/2/2017 | Transfer | Correct service item below | * | | both services | conduit for ground wire must be bonded at both sides or use PVC |
| 11/2/2017 | Transfer | Correct service item below | * | | MCC building | lugs must be listed for fine strand wire or use compression termination pins |
| 11/2/2017 | Transfer | Correct service item below | * | | both services | placards required for available fault current/date calculated |
| 11/2/2017 | Transfer | Correct service item below | * | | foam building | exterior main disconnect/ground rods required |