Muni.org > Departments > Development Services> Permit Information & Inspection Request
Click Here To View Another Inspection


Inspection #: 486395
Inspection Type: Gas Piping
Inspector: Y.Dovba
Result: Approved
Comment: Medium gas piping rough-in and tests Approved. 15 RTUs installed and through the roof, S/A & R/A ducting will be completed by T.I. contractor. NOTE: 15-gas regulaors installed with all required test tees. NOTE 2) Low pressure piping downstream the regulators is 6''-12'' sections of pipe, service tested by contractor. Green tag issued.

Inspection Corrections
DateStatusCodeDescriptionRefLocationComments
       