| Date | Status | Code | Description | Ref | Location | Comments |
| 3/20/2014 | Transfer | EF1 | Correct Below | | Panel B | Breaker locks for water heater must be fastened to the breakers. |
| 3/20/2014 | Transfer | EF1 | Correct Below | | | |
| 3/20/2014 | Transfer | EF1 | Correct Below | | Site lighting poles. | Ground wire needs to be #10 AWG to match current carrying conductors. |
| 3/20/2014 | Transfer | EF1 | Correct Below | | 1st floor electric water heater. | Label as to source of supply. Breaker locks. |
| 3/20/2014 | Transfer | EF1 | Correct Below | | Main entry. | Install chandalier. |
| 3/20/2014 | Transfer | EF1 | Correct Below | | Stairwell | EM battery light needs to be on stairwell circuit. |
| 3/20/2014 | Transfer | EF1 | Correct Below | | Various | Blank off switches for lights that are not to be installed. |