Inspection #: 196639
Inspection Type: Final Electrical
Inspector: D.Rooney
Result: Partial
Comment: Inspect listings noted on previous inspection. Inspect RTUs run at low speed when Generator is on. 1:00pm is when the control contractor and Justin will be there for this. Would like CCO open for business until Dec.31. The radiology and mamagram will not be done. Radiology is scheduled for mid September and mamogram is suppose to arrive late October. Thanks. . Requested by: Curt Birch 232-8778 curt@qealaska.com

Inspection Corrections
DateStatusCodeDescriptionRefLocationComments
8/16/2012TransferEF1Correct Below  x-ray and mamogram equipment not yet installed.
8/16/2012TransferElecRoughOther000 Electrical Rough OtherPlease correct the following:Do approved dwgs show genset as Art. 702? 
8/16/2012TransferElecRoughOther000 Electrical Rough OtherPlease correct the following:Check 110.26 working clearances for 1st fl electric room. 
8/16/2012TransferElecRoughOther000 Electrical Rough OtherPlease correct the following:Verify GFP service disconnect in ATS. 
8/16/2012TransferElecRoughOther000 Electrical Rough OtherPlease correct the following:Verify 4-pole ATS. (genset gnd and neut. bonded) 
8/16/2012TransferElecRoughOther000 Electrical Rough OtherPlease correct the following:  
8/16/2012TransferElecRoughOther000 Electrical Rough OtherPlease correct the following:Genset shown on dwgs as 1200A. Actual installation is 800A genset. MDP load calc is over 900A. Dwgs need to doccument solution. 
8/16/2012TransferEF1Correct Below Boiler roomController for pumps 4, 5 and 11 are too big. Controollers only suitable for 6amps or more and pumps are rated less that 3 amps.
8/16/2012TransferEF1Correct Below In server roomOutlets for server racks are not yet installed.
8/16/2012TransferEF1Correct Below Boiler roomPumps 9 and 11 do not appear to have a third parts liisting.
8/16/2012TransferEF1Correct Below Pod Bcord installed for scale not permitted inside wall
8/16/2012TransferEF1Correct Below Boiler roomSome disconnects/motor controllers need bonnding bushings at knockouts.
8/16/2012TransferElecRoughOther000 Electrical Rough OtherPlease correct the following:Provide latest approved dwgs/change orders 