| Date | Status | Code | Description | Ref | Location | Comments |
| 8/15/2012 | | EF1 | Correct Below | | vfd workspace at penthouse | |
| 8/15/2012 | | ElecRoughOther | 000 Electrical Rough Other | Please correct the following: | Conditional electrical final approved until 8-15-2012. | |
| 8/15/2012 | | ElecRoughOther | 000 Electrical Rough Other | Please correct the following: | Parking lot light poles not completed. | |
| 8/15/2012 | | ElecRoughOther | 000 Electrical Rough Other | Please correct the following: | Penthouse VFD's need placcarding due to impropper working clearances. | |
| 8/15/2012 | | EF1 | Correct Below | | placards at service | |
| 8/15/2012 | | EF1 | Correct Below | | panel schedules incomplete (all floors) | |
| 8/15/2012 | | EF1 | Correct Below | | em lights at center row first floor have no power | |
| 8/15/2012 | | EF1 | Correct Below | | heat trace incomplete | |
| 8/15/2012 | | EF1 | Correct Below | | north and west lightpoles incomplete | |
| 8/15/2012 | | EF1 | Correct Below | | no power ar west parking lot gfcis | |
| 7/10/2012 | | EF1 | Correct Below | | Mechanical room -:lighting contactor | |
| 7/10/2012 | | EF1 | Correct Below | | Mechanical room:between boilers | |
| 7/10/2012 | | EF1 | Correct Below | | Mechanical room:far right corner | |